Monday, February 19, 2007

New Downtown Hotel RFP and Info

Read It Here First

If you've been following the Harrison Square project, you know that the City of Fort Wayne recently sent out a Request For Proposals (RFP) document for a new downtown hotel, which resulted in a proposal for a full-service Marriott to be located at the current site of Belmont Beverage, on the corner of Jefferson and Harrison.

If you've been waiting to read the RFP for yourself, then wait no more! Simply click the links below to peruse the RFP and related documents.

Request For Proposals For Convention Center Hotel Development (PDF)

Request For Proposals Addendum (PDF)

Summary Of Submitted Questions (PDF)

Basemap (PDF)

Comments? Concerns?
State your ideas, feelings, and opinions here!

1 comments:

LP Mike Sylvester said...

The Redevelopment Commission of the City of Fort Wayne issued a "Request for Proposal" for the "Convention Center Hotel Development" on December 21st, 2006.

The formal "RFP" confirms some of the things that I have suspected for a long time.

Last Thursday I had a chance to talk to the Mayor in a public forum and ask him about the project. We had a friendly exchange and he said that he did not know the answers to my specific questions; he said that the project was still in the planning stages. The Mayor promised me that I could meet with The City of Fort Wayne so that I can review the financial projections for the project when they are completed and before they are voted on by City Council. I am looking forward to that meeting!

According to the original RFP:
The RFP was issued on Dec 21st, 2007 (Cover page)
The RFP requires the hotel to have 300+ rooms (Page four, section 2.1)
The RFP states that “The hotel program must include a minimum of 300 rooms to be considered responsive” (page 4, section 2.4)
The RFP requires proposals to be submitted to the City by 5 PM on Feb 13th, 2007 (Page 12, section 13.3)
The RFP stipulates that “a refundable deposit in escrow of $300,000” will be established by the Respondent (page 5, section 3.4)

The RFP was amended with Addendum Number 2 on January 17th, 2007. The amendment says that “The City of Fort Wayne is willing to negotiate the number of rooms for the hotel and will consider lowering the number of rooms that are now set at 300.”

One “Respondent” requested that the deposit be lowered; Fort Wayne immediately waived the deposit requirement, page 3 of the written questions submitted by the Respondents.

Other interesting items:

1. “A portion of the Parking Garage revenues can be directed to support hotel operations,” page 4, section 1.3.
2. “Parking will be provided in the 900 space garage,” page 4, section 2.3.
3. “The City will pursue negotiations with the top ranked Respondent with the goal of a Development Agreement by April 1st, 2007,” page 11, section 10.3.

I have several questions about this RFP:

1. From the first day this project was “unveiled” every official press release and communication from The City of Fort Wayne has stated that “for the project to be economically viable the hotel must have 300 rooms or more.” Why was this requirement removed from the RFP on January 17th, 2007?

2. Requiring a minimal deposit of $300,000 for a project of this magnitude seems very low to me. Why was this requirement waived?

3. This is a large project that requires a large amount of planning. Why does Fort Wayne want to have a Development Agreement in place by April 1st, 2007?

I have a lot more questions about this project and I am greatly looking forward to
meeting with The City of Fort Wayne and analyzing the financial projections.

I applaud the Mayor for allowing an independent citizen to review this project
BEFORE it is voted on by our City Council!

Mike Sylvester