The Redevelopment Commission held a special meeting today to open a number of bid packages for the construction of the Harrison Square ballpark.
The amounts for the bids are listed below beneath each bid package.
Package #6 Masonry
Complete Masonry Services, Inc
Yorktown, IN
Base bid - $878,940
Hagerman
Fort Wayne, IN
Base bid - $839,500
Package #7 Miscellaneous metals and handrails
Nationwide Construction Group
Chesterfield, MI
Base bid - $827,522
Also placed a bid for package #19 Fences and gates
Base bid - $119,655
A combined bid for package 7 and 19 together was $920,000
Hartman Products
Bluffton, IN
Base bid - $857,000
Almet Inc
New Haven, IN
Base bid - $934,800
Fort Wayne Structural Products
Fort Wayne, IN
Base bid - $926,000
Package #8 General Building Construction
Muhlenkamp Building Corporation
Celina, OH
Base bid - $1,675,134
Hagerman
Fort Wayne, IN
Base bid - $1,892,000
Schenkel & Sons Inc
Fort Wayne, IN
Base bid - $1,405,000
Michael Kinder and Sons
Fort Wayne, IN
Base bid - $1,448,000
Package #9 Roofing and sheet metal
CMS Roofing
Fort Wayne, IN
Base bid - $592,600
C. L. Schust
Fort Wayne, IN
Base bid - $764,300
Pettigrew & Sons Inc
Fort Wayne, IN
Base bid - $594,400
Fort Wayne Roofing and Sheet Metal
Fort Wayne, IN
Base bid - $528,900
Package #10 Glass and glazing
Celina Glass
Celina, OH
Base bid - $820,000
SPS Corporation
Fort Wayne, IN
Base bid - $560,000
Hall Aluminum Products Inc
Fort Wayne, IN
Base bid - $465,700
Package #11 Metal studs and drywall
Rosema Construction
Fort Wayne, IN
Base bid - $1,610,000
Strahm Group Inc
Fort Wayne, IN
Base bid - $1,722,500
Also placed a bid for package #12 Flooring
Base bid - $277,600
A combined bid for package 11 and 12 together was $1,973,000
Performance Contracting Inc
Carmel, IN
Base bid - $1,780,000
Package #12 Flooring
Jack Laurie Commercial Floors
Fort Wayne, IN
Base bid - $223,949
Tile Interiors Inc
Fort Wayne, IN
Base bid - $207,200
Package #13 painting
Thomarios
Akron, OH
Base bid - $536,070
Package #16 Fire protection
VFP Fire Systems
Fort Wayne, IN
Base bid - $233,512
Ryan Fire Protection
Noblesville, IN
Base bid - $287,000
Shambaugh and Son
Fort Wayne, IN
Base bid - $276,386
Package #18 Playing field
Sports Construction Group
Cleveland, OH
Base bid - $1,505,000
MJM Services
Belleville, IL
Base bid - $1,387,835
Motz Group
Cincinnati, OH
Base bid - $1,019,796
Tom's Landscaping Inc
Troy, MI
Base bid - $726,774
Fleming Excavating
Decatur, IN
Base bid - $1,299,865
Package #19 Fences and gates
Arrow Fence
Fort Wayne, IN
Base bid - $158,600
RNC Fence
Fort Wayne, IN
Base bid - $198,250
Eagle Fence
Fort Wayne, IN
Base bid - $116,850
Percentage of Fort Wayne based companies making bids: 57%
The lowest combined total for the bid packages (estimated as about $7M worth of work) is $7,472,656.
The next meeting of the Redevelopment Commission will take place on Monday, March 17 at 4PM.